„Technical Design Control and Construction Supervision of FIDIC Yellow and Red Book Contracts within project № DIR – 51011116 – 23 Integrated Water Cycle for the City of Shumen – II phase, OP “Environment 2007 – 2013“, including:
Lot 1 – Reconstruction and Extension of WWTP (FIDIC Yellow Book);
Lot 2 – Construction and Rehabilitation of Water Supply and Sewerage Network and 2 Sewerage Pumping Stations (FIDIC Yellow Book);
Lot 3 – Construction of Sewerage Pumping Station „Divdyadivi“ (FIDIC Red Book)
– Use Permit №СТ-05-880/06.06.2016 (Lot 2)
Value: Consultancy Services – 2 806 650 levs; Construction Works: Lot 1 – 22 793 282,33 levs; Lot 2 – 31 456 789,13 levs; Lot 3 –
2 100 198,56 levs;
Date of conclusion of the contract: 11.09.2013